A 600 kWh battery system is to be installed in a trial on board the Maersk Cape Town in December to improve vessel performance and reduce carbon emissions.

“This trial will provide a greater understanding of energy storage that will support Maersk in moving towards further electrification of its fleet and port terminals. Maersk will continue to facilitate, test, and develop low-carbon solutions on our journey to become carbon neutral by 2050,” Søren Toft, Maersk chief operations officer, said.

Propelling marine vessels with battery power alone is still years away from being a technically- and economically-viable option. However marine battery systems can be used to improve the efficiency of a vessel’s onboard electrical systems such as the generators of the Maersk Cape Town. By maintaining the vessel’s auxiliary generators at a more optimal load, and avoiding running generators when not needed, overall fuel consumption can be reduced.

Additionally, it is to support the generators with up to 1,800 kVA of power during rapid changes in electrical load such as thruster operation. This can reduce generator maintenance requirements. The battery system is also capable of providing redundant power, which can improve reliability at sea by ensuring continuous power supply.

ADVERTISEMENT  

The Maersk Cape Town includes a waste heat recovery system, which is a special feature of many Maersk container vessels. This system increases overall efficiency, as it allows the batteries to charge by capturing electrical energy from heat that would otherwise have been lost out of the exhaust gas system for the main propulsion.

“This exciting pilot – the first of its kind in the industry – will show the potential of battery technologies to keep improving the performance of our vessels while also reducing fuel consumption in our non-propulsion electrical systems,” Ole Graa, Maersk head of fleet technology said.

A time-lapse video of the battery project can be viewed here.

The containerised battery energy storage system has been manufactured in Odense, Denmark by the system integrator and turnkey supplier Trident Maritime Systems. The battery system will be transported to Singapore and installed on board the Maersk Cape Town.

The vessel is a Singapore-flagged 249-metre long container ship built in 2011 that sails between West Africa and East Asia. The first full voyage with the new system in place will take place next year and will be closely monitored to evaluate the performance of the system against the trial’s ambitions.

Battery modules will be operating within the container in conjunction with other electrical and control components. Maersk has also worked in close collaboration with the American Bureau of Shipping – the vessel’s classification society – to ensure safety and compliance.